Risks and issues management

Risk and issues management is a process of identifying and assessing risks associated with a project, with the aim of managing their impact on the project.

Risks

A risk is any threat of an event that may have a negative impact to the project, and which may be neutralized, or at least minimized, through pre-defined actions.

Possibility to define indicators to follow the respect of dates values.

The risk management plan is a key point to project management:

  • Identify risks and estimate their severity and likelihood.

  • Identify mitigating actions.

  • Identify opportunities.

  • Follow-up actions.

  • Identify risks that finally occur (becoming an issue).

Contingency reserve

  • Contingency reserve is defined according to monetary impact and likelihood of occurrence.

  • Contingency reserve for risks and potential gain for opportunities allow to define the project reserve.

Note

Field Criticality: Automatically calculated from Severity and Likelihood values. Value can be changed.

Field Project reserved cost: Automatically calculated from the percentage defined for the selected likelihood. (See: Likelihoods)

Opportunities

An opportunity can be seen as a positive risk. It is not a threat but the opportunity to have a positive impact to the project.

Potential gain

The potential gain is defined according to the expected amount and likelihood of occurrence.

Contingency reserve for risks and potential gain for opportunities allow to define the project reserve.

Note

Field Criticality: Automatically calculated from Significance and Likelihood values. See: Criticality value calculation - Value can be changed.

Field Project reserved gain: Automatically calculated from the percentage defined for the selected likelihood. (See: Likelihoods)

See also

Project reserve

Criticality value calculation

Criticality value is automatically calculated from Severity (Significance) and Likelihood values.

Criticality, Severity (Significance) and Likelihood values are defined in lists of values screens.

In the previous screens, a name of value is set with numeric value.

Criticality numeric value is determined by a simple equation as follows:

Default values are determined. You can change its values while respecting the equation defined above.

Note

Equation

  • [Criticality value] = [Severity value] X [Likelihood value] / 2

  • For example: Critical (8) = High (4) X High (4) / 2

See also

Criticalities, Severities and Likelihoods screens.

Issues

An issue is a problem that occurs during the project.

If the risk Management plan has been correctly managed, issues should always be occurring identified risks.

Actions must be defined to solve the issue.

Possibility to define indicators to follow the respect of dates values.

Actions

An action is a task or activity that is set-up in order to :

  • Reduce the likelihood of a risk

  • or reduce the impact of a risk

  • or solve an issue

  • or build a post-meeting action plan

  • or just define a “to do list”.

The actions are the main activities of the risk management plan.

They must be regularly followed-up.

Private actions allow to manage a personal to-do list.

Possibility to define indicators to follow the respect of dates values.